The Real Evergreen Line Story

The Real Evergreen Line Story

Summary: Most people are still asking the question of why the province decided to suddenly switch the Evergreen Line to SkyTrain technology in 2008. I think we should be asking questions about why the LRT design process suddenly stopped, with no reason, back in 2007.


The Evergreen Line is now slated to open in 2017, which just happens to be yet another delay in a consecutive series. Nobody likes delays, and these Evergreen Line delays have injected a new wave of doubt among transit observers here in Metro Vancouver, who may remember a time not too long ago when the Evergreen Line was comparable to a hot potato. That is, hardly anyone could come to an agreement about it.

1998 SkyTrain plans for the Millennium Line. Today’s “Evergreen Line” was supposed to be part of the Millennium Line’s second phase.

During the late 2000s, what is now the Evergreen Line had to go through numerous obstacles, ranging from funding shortages to planning issues to a lack of clarity in the political commitment to the line itself. The Evergreen Line was first proposed as the second phase of what became the Millennium Line SkyTrain, cancelled along with a switch in government, and then brought back to life later on as an at-grade Light Rail Transit proposal on the original alignment.

However, perhaps one of the most perplexing twists in the Evergreen Line story was the controversial change from an at-grade Light Rail Transit system, to the currently-being built extension of the existing SkyTrain system. It took people by surprise, changed the focus of the discussion and was so significant that it caught the attention of transit bloggers in other Canadian cities.

The move was controversial because of the creation of a new business case released by the provincial government (hereafter referred to as the “2008 business case”) that overrode a previous business case released by TransLink (the “2006 business case”) for the Evergreen Line LRT. A following, final business case by the province (the “2010 business case”) adopted the results of the 2008 business case without making major changes to it, or addressing its supposed issues.

The 2008 business case explained that its recommendation for SkyTrain (ALRT) on the current corridor was based on 4 key findings:

  1. Ridership – ALRT will produce two and a half times the ridership of Light Rail Transit (LRT) technology; this is consistent with the ridership goals in the Provincial Transit Plan.
  2. Travel Time – ALRT will move people almost twice as fast as LRT (in the NW corridor).
  3. Benefits and Cost – ALRT will achieve greater ridership and improved travel times at a capital cost of $1.4 billion, with overall benefit-cost ratio that favour ALRT over LRT.
  4. System Integration – ALRT will integrate into TransLink’s existing SkyTrain system more efficiently than LRT.

The new business case recommended SkyTrain based on finding advantages in 4 key areas: Ridership; Travel Time; Benefits and Cost; and System Integration.

Light Rail advocates who looked into the study insisted that the new analysis was biased in favour of SkyTrain, saying it rejected what was an already-sound business case. Some of these people alleged that the switch was a result of insider connections, shady agreements, and other under-the-radar proceedings. 2008 was a time when it wasn’t as clear to people that SkyTrain isn’t a proprietary transit technology and it was probably no surprise that critics of the decision showed up in waves.

These critics were joined by others, including City Councils of the time, who expressed concern about some aspects of the newer business case. Two particular major players come into mind:

1. The City of Burnaby released a staff report that injected doubt into the Evergreen Line’s cost estimates, ridership estimates and evaluation. (See [HERE] for report)

“This report recommends that the Province and TransLink undertake to re-evaluate the choice of technology and prepare a business case of LRT technology for the Evergreen Line based on the concerns and questions raised in this report with regard to service speed, ridership estimates, operating and capital costs, inter-operability, community service and other factors.”

2. A Portland-based transportation engineer named Gerald Fox alleged that the analysis had been manipulated to favour SkyTrain. (The original letter was posted [HERE]).

“It is interesting how TransLink has used this cunning method of manipulating analysis to justify SkyTrain in corridor after corridor, and has thus succeeded in keeping its proprietary rail system expanding.”

At the time, no one could present an argument strong enough to combat what seemed to be a legitimate series of concerns on the SkyTrain proposal. The decisions of 2008 and the surrounding controversy continue to be reflected in the words of today’s writers, most recently surfacing with the announcement of the recent Evergreen Line delay and the ongoing SkyTrain versus LRT debate in Surrey.

It is, however, important to remember that when the Auditor General of British Columbia was asked to look into the Evergreen Line technology switch, the finished report in 2013 concluded that while some information was missing, the switch to SkyTrain was the right decision.

The Auditor General summarized the missing information as a shortfall in explaining the following:

  • Options’ risks, costs and benefits;
  • Assumptions underpinning SkyTrain ridership;
  • Wider transit system risks and dependencies; and
  • How agencies would measure performance

In the approximately 3 years since this Audit was released and the 7 years since the decision to switch to SkyTrain, new information has been released that makes it possible to fill in all four of these gaps, as well as the other concerns raised by critics and the City of Burnaby.

In an effort to compile this new information, I performed the research myself, which included extensively looking into all business cases (2006, 2008 and 2010) and other supporting evidence (including all 61 archived pages of the original Evergreen Line LRT discussion thread on Skyscraperpage).

With my conclusion that the Evergreen Line business case was not manipulated to favour SkyTrain, I present my results below.

1. Were SkyTrain and LRT compared properly?

The first and foremost concern by the auditor general was that the SkyTrain and LRT options may not have been compared properly, citing that numerous numbers in the comparison were skewed and contained significantly shortfalls.

The City of Burnaby’s staff report probably best summarized the issues that were raised surrounding the comparison. They are:

Capital cost estimates

As the capital cost estimates for LRT increased from $970 million (2006 business case) to $1.25 billion (2008 business case) with little explanation, the City of Burnaby complained that this increase was unreasonable – especially as it brought the cost difference with SkyTrain down to a mere $150 million (12%). Light Rail advocates and critics, including Gerald Fox, complained that the cost increase was manipulated to favour SkyTrain.

It was noted in the 2006 study that the cost estimate of then was done at a 90% preliminary design stage – not a fully detailed design stage presenting a finalized cost. It thus seems conceivable that costs increased while the final alternative was being analyzed for the 2008 business case.

Recently I performed some research on the capital costs of Canadian rail transit systems. With several rapid transit and light rail systems now proposed across the country, I took the opportunity to compile an inflation-adjusted comparison of the projects’ capital costs – adjusting each project for the amount of grade-separation (tunnelled, or elevated) and using that as a guideline to compare the costs. This extensive research took me several weeks to complete as I had to manually measure most of the proposals to assess the amount of grade-separation.

See: Capital costs of Canadian rail transit systems

Unsurprisingly, I reached the conclusion that – with the steepest trend in perecentage-to-cost – bored tunnel is the most expensive alignment to construct.

The Evergreen Line, no matter whether it were to be SkyTrain or Light Rail Transit, has a 2km bored tunnel as a part of its alignment through the mountainous terrain between Burquitlam and Port Moody. This accounts for about 20% of the entire route.

The Evergreen Line's 2006 estimate is marked by the "$99" at the bottom left. The 2008 estimate is the $112 above it.
(Open to enlarge) – The Evergreen Line’s 2006 estimate is marked by the “$99” at the bottom left. The 2008 estimate is the $112 above it.

My measurements indicated that the 2006 cost-per-km estimates were the lowest of the other projects. The estimate was significantly below other projects with a ~20% bored tunnel percentage, and below the average trend line that related percentage in a tunnel to rapid transit cost per km.

In other words, the 2006 cost estimates are too low and were probably incorrect.

Now that we know how much trouble it took to construct the Evergreen Line’s 2km tunnel, it’s certain that the LRT project’s final cost would have come closer to $1.25 billion. LRT tunnels need to account for pantographs and higher vehicle heights; whereas the linear motors used on our SkyTrain technology lines are more optimal for tunnels as the train is lower and closer to the ground. As a result, an LRT tunnel would have been larger and more complex and would have likely lead to additional potential problems, necessitating a higher contingency budget.

Just imagine what kind of liability chaos there’d be if a sinkhole did open under a home above the tunnel route. It hasn’t happened with our SkyTrain tunnel, but it’d be more likely under a larger tunnel (and a larger, more powerful tunnel boring machine) needed for an LRT tunnel.

Operating costs

Most critics were adamant to point out that the operating costs rose from $12.21 million in 2006, to $15.3 million in 2008 (both measurements were in 2007 dollars). What was overlooked by these critics is that the cost increase can be explained by a difference in service frequency.

The 2006 business case’s estimate was based on a 6 minute initial operating frequency. The 2008 business case’s operating costs were based on a higher 5 minute initial operating frequency to presumably make the LRT service more competitive and boost its business case (the higher frequency would have also added additional trains, explaining part of the capital cost increase). Whereas the 2008 cost estimates are 25% higher while a 5 minute frequency is 20% higher than 6, the newer numbers seem just about right to me.

Travel times

The City of Burnaby’s assessment of travel times suggested that the SkyTrain alternative’s travel time estimates were far too high and the LRT alternative’s estimates were far too low. It provided this graphic to show the disparity:

Evergreen Line graphic
Open to enlarge

Burnaby complained that the Evergreen Line’s LRT speed estimates were lower than two existing LRT systems in Canada (Calgary and Edmonton).

However, most of Calgary and Edmonton’s LRT systems are built off-street, and with gated crossings and absolute priority like railway systems. Most of the Evergreen Line as an LRT would be in the middle of streets and would have to follow the roadway speed limits (typically 50-60km/h). Naturally, this would result in slower average speeds than Calgary and Edmonton, where trains may run at 80km/h on dedicated rights-of-way.

While the SkyTrain alternative had much higher average speeds than the existing Expo & Millennium Lines (average of 43km/h), the addition of Lincoln Station to the proposal has added some length to the travel time to the extent that the Evegreen Line’s end-to-end travel time is now usually described as 15 minutes – an average speed of 43.6km/h.

At the end of the day, these differences aren’t really dictated by the transit technology. The Evergreen Line will have the system’s longest station-less segment, which is largely in part due to the 2km tunnel between Burquitlam and Port Moody stations. The higher average speeds near here would be comparable to other long sections crossing geographical features, such as the 2.3km SkyBridge segment on the Expo Line over the Fraser River.

Maximum speed

Gerald Fox also raised an issue that the stated maximum LRT speed in the 2008 business case (60km/h) was lower than the potential speed limits that could be achieved in the off-street, 2km tunnel – claiming that the 2006 business case accounted for faster running speeds of up to 80km/h inside the tunnel.

However, the end-to-end travel time estimates in the 2008 business case were actually lower than that of the 2006 business case by 0.4 minutes.

The 60km/h expression in the 2008 business case was probably meant to highlight the speed on most of the on-street sections (outside of the tunnel), which accounted for as much as 80% of the route.

In conclusion

Based on the data I’ve collected above it is clear that SkyTrain and LRT were not compared unfairly.

There is little reason to believe that the 2008 business case was wrong in assumptions. There could’ve been better distribution of the info at hand, and some improvements in the planning process (like the addition of Lincoln Station from the beginning). However, no skewering of the numbers and manipulation to favour SkyTrain has taken place.

2. Was ridership over-estimated?

Ridership was an additional concern raised by the City of Burnaby, which complained that the ridership estimates for the SkyTrain option (at 2.1 million passengers annually/km) were too high,  and that the LRT ridership estimates were too low. Burnaby complained that the 2008 business case did not provide a proper explanation of how ridership was estimated.

Open to enlarge
Open to enlarge

The LRT ridership estimates were said to be too low because they were lower than two existing Canadian LRT systems (40% lower than Calgary, and 9% lower than Edmonton). For the same reasons as I explained above, it’s not possible to put the Edmonton and Calgary systems in the same category as an Evergreen Line LRT. The Evergreen Line LRT is largely on-street; the Calgary and Edmonton systems are not, and tend to run on exclusive rights-of-way at speeds of 80km/h.

This leaves the high ridership estimates with the SkyTrain system. The auditor general raised an issue that the SkyTrain ridership assumptions with the Evergreen Line were made with assumptions that a completed transit network would be built by 2021 following the 2008 Provincial Transit Plan. This included SkyTrain extensions in Broadway and Surrey, neither of which will be built by 2021 based on the current situation.

Burnaby complained that at 2.10 million annual passengers per km, the estimates were higher than the existing SkyTrain system (1.60 million annual passengers per km) and thus much higher than would be realistic.

However, it’s important to note that the SkyTrain ridership estimate in Burnaby’s report was taken before the Canada Line to Richmond was introduced in 2009. The Canada Line’s opening broke ridership records with ridership almost immediately shooting up to its current level of 40.2 million passengers per year or over 120,000 per weekday – numbers that were well ahead of schedule even beat entire, city-wide LRT systems in ridership.

When this annual ridership is worked out per-km, the Canada Line is carrying 2.10 million annual passengers per km – the same amount that was projected for the Evergreen Line – and as such is also contributing to an increase in the system-wide value.

As costly as infrastructure like the Canada Line SkyTrain is, the investment has been proven worthy by the benefits to the tens of thousands of people using the system daily. The investment confidence that has resulted in our SkyTrain system expansions needs to be applied to the whole system.
As costly as infrastructure like the Canada Line SkyTrain is, the investment has been proven worthy by the benefits to the tens of thousands of people using the system daily.

A huge part of the reason the Canada Line was so successful was because efforts by the City of Richmond to make the elevated segment on No. 3 Road at-grade (like a light rail system) were defeated, resulting in the construction of a fully grade-separated line. The full grade-separation enabled higher trip speeds, which have been cited in rider surveys as the #1 most-liked aspect of the Canada Line system – outpacing every other favourable aspect mentioned by riders.

The Evergreen Line’s SkyTrain switch decision was largely based on favouring the faster travel-times and transferless journeys of a SkyTrain system. It’s thus conceivable that the Evergreen Line could see the same kind of ridership success that the Canada Line did.

3. Were the risks properly and thoroughly assessed?

The auditor general commented that the 2008 and 2010 business cases did not provide information on the risks that came with connecting Evergreen Line outcomes with the performance of other parts of our regional transit system. In particular, the Evergreen Line’s performance estimates did not account for the potential impacts of:

  1. the level and coverage of bus connector services on ridership;
  2. parking at the more popular Evergreen stations;
  3. changes to the West Coast Express (WCE), which provides peak commuter services for passengers who want to travel between the northeast Metro Vancouver and downtown Vancouver
  4. Evergreen services on those parts of the SkyTrain system that are near or at capacity in the commuting peak periods (for example, around Broadway station).

These concerns present significant risks and it is of my opinion that they should have been addressed.

However, accounting for these risks whenever a large transit priority is laid out in our region is hardly ever common practice. Today’s transit projects have continued the practice of tying performance estimates to grandiose plans for the rest of the regional transit system, like the transit vision crafted by the Regional Mayors’ Council that was defeated in the March 2015 referendum.

When the 2015 referendum was defeated, so too were the additional commitments to connecting bus service that would have been critical to the success of the included rapid transit projects. It’s raised concern among decision-makers such as Coquitlam Mayor Richard Stewart, for example, who raised a concern with the potential costs of increasing parking as additional bus services connecting to the Evergreen Line were rejected along with the other proposals.

Nevertheless, local governments have forged ahead in planning for these lines, despite the new risks created with the lack of a regional vision component. As I believe that there will be opportunities in the future to return to those other critical transit priorities, continuing planning anyway – rather than letting all transit priorities come to a halt – is the best practice.

4.  How are we going to measure performance?

The last issue concerned the collection of performance data to measure performance after the line’s opening. No framework had been set in the 2008 and 2010 business cases, and the lack of such a framework would have a consequence on future transit planning.

However, the Auditor did acknowledge in his report that a framework could still be completed in time for the line’s opening. Although it remains to be said if the province has followed through on this recommendation, this issue isn’t relatively as much of a concern as the others as it has an immediate, clear solution.


So what’s the real “Evergreen Line Story”?

When the Evergreen Line was changed to a SkyTrain extension project in 2008, the switch came after an extended halt in design work and public consultation.

Like today’s rapid transit projects, the Evergreen Line was determined through a multiple-account evaluation that includes a Phase 1 (draft option comparison), Phase 2 (detailed option comparison) and a Phase 3 (finalized option comparison and detailed design).

The 2006 study was finalized at the phase 2 stage, and it noted that its cost estimates were done at the 90% preliminary design stage.

After that, there was silence in the project design work.

At the time, there were plenty of issues around project funding (which can be backtracked to on the Skyscraperpage archives). I can understand delays with transit funding (still a very big issue with projects today). However, the funding issue shouldn’t have delayed detailed design work on the Evergreen Line LRT project. For awhile we didn’t hear anything from planners, politicians or anyone involved regarding the project’s design until rumours of a major announcement surfaced in January 2008. The final business case that was then released in February had been completed by the province rather than TransLink.

For awhile we didn’t hear anything from planners, politicians or anyone involved regarding the project’s design

So it honestly has me raising questions: what exactly was going on? Why did Evergreen Line design works come to a stop, and why didn’t the next phase of consultations take place? Did planners at TransLink realize they under-estimated the LRT costs, and had nervousy about going public with the news? Did local governments start losing confidence in the at-grade project’s business case?

There’s all these disconnects that don’t seem to make sense, and I would argue that this should have been of far greater concern than the provincial government’s decision to switch the project to SkyTrain. It’s not the province’s fault the planning department of the time had decided to cut us off for just over a year on the project’s progress. It’s almost as if the sudden switch to SkyTrain was a measure to deal with these serious problems.

All I do know is that in October 2007, the B.C. Finance minister came to the public with a statement that the Evergreen Line’s progress had indeed been frozen, but that it wasn’t due to the funding shortfall

Finance minister Carole Taylor: The premier did say last week that the Evergreen will be built. The funding is not holding it up. They haven’t decided on exactly the route and exactly the stops. So, we have made the commitment to financially be there when everybody’s ready to go.

(Above quote from: Evergreen Line not held up by funding, finance minister says – Coquitlam NOW)

This almost certainly indicates that the LRT planning department had run into issues with the design, since the 2006 business case had anticipated the start of construction by September 2007.

Instead, in October 2007 the design hadn’t been finished and the planners in-charge “hadn’t decided on exactly the route and exactly the stops.”

You be the judge, but it sounds a heck of a lot like that the province managed to narrowly get us out of an Evergreen Line LRT fiasco in its decision to build SkyTrain instead.


Jaded by SkyTrain and a lack of LRT

There hasn’t been a single, grade-level Light Rail project approved in this region except for the currently proposed project in Surrey, and that’s probably what has raised the irk of some people who have been enthusiastic about the idea of at-grade rail. It’s probably why there’s a commonly-held belief that only provincial government overrides result in SkyTrain, and that at-grade Light Rail systems don’t have major shortfalls of their own that have resulted in their rejection here in Metro Vancouver so far.

However, the argument that lack of at-grade rail infrastructure in this region really caused us to lose out on transit benefits (i.e. we could have built a bigger transit network!) is entirely debatable. The benefits of SkyTrain should be clear to decision-makers, planners and transit enthusiasts in our region.

Despite the constant use of grade-separation and SkyTrain technology, Metro Vancouver’s SkyTrain network expanded at a faster pace than any other system in Canada. Vancouver’s rapid transit growth has lead Canadian cities – and when the Evergreen Line opens to the public next year, we’ll have the longest rapid transit system in Canada spanning nearly 80km – and the longest driverless transit network in the world. The lower operating costs of driverless trains make it possible to keep expanding our transit network without bankrupting our operating budget on the cost of drivers.

Despite the constant use of grade-separation and SkyTrain technology, Metro Vancouver’s SkyTrain network expanded at a faster pace than any other system in Canada.

SkyTrain also has the highest ridership of any rapid transit system in North America that isn’t classified as “heavy” rail. At nearly 9,000 boarding passengers per kilometre, SkyTrain outperforms every single at-grade rail system in Canada and the U.S.

SkyTrain ridership/km vs. other transit systems

Data is from the American Public Transit Association (Q3 2014) unless stated

City System name (type) Weekday daily boardings Daily boardings/mile
Vancouver SkyTrain (driverless) 377,900 8,870
Calgary C-Train (LRT) 310,700 8,510
Boston MBTA light rail (LRT) 214,500 8,250
Edmonton Light Rail Transit (LRT) 98,144* 7,550
Toronto Streetcar (on-street) 281,900 5,525
San Francisco Muni Metro (LRT) 145,500 4,076
Houston METRORail (LRT) 45,700 3,571
Newark Newark/Hudson Bergen LRT 72,939** 3,143
Minneapolis METRO Light Rail (LRT) 64,500 2,938
Los Angeles Metro Rail (LRT) 203,400 2,892
Seattle Link Light Rail (LRT) 40,300 2,330
Portland MAX, Streetcar (LRT) 113,900 2,330
San Diego Trolley (LRT) 124,100 2,320
Phoenix Valley Metro (LRT) 41,200 2,060

* Q3 numbers were not reported. Data from Edmonton Transit, collected during the same period, used instead.
** Q3 numbers were not reported. NJ Transit’s own FY2014 data is used in place (the same number is reported in APTA’s Q4 ridership report).


On top of everything, SkyTrain has made us one of the most successful metropolitan areas in transit ridership with an annual ridership per capita that is 3rd highest on this continent (beat only by New York City and Greater Toronto)

Region Population Annual Ridership
(thousands)
Annual Ridership
(per capita)
New York City 19,831,858 3,893,854 196
Greater Toronto 5,583,064 1,003,230 180
Metro Vancouver 2,313,328 363,163 157
Calgary 1,120,225 157,325 140
Montreal 3,824,221 433,710 113
Boston 4,640,802 399,594 86
Washington, DC 5,860,342 456,915 78
San Francisco Bay 6,349,948 476,219 75
Chicago 9,522,434 658,203 69
Philadelphia 6,018,800 336,981 56
Los Angeles 13,052,921 620,903 48
Seattle/Puget Sound Region 3,807,148 175,215 46

Data above from South Fraser Blog

With these thoughts laid out, I’d like to see anyone try to claim that decisions resulting in SkyTrain projects over LRT are solely a result of senior-government overrides.

…or that anyone’s manipulating data to favour SkyTrain in rapid transit studies, because that’s simply not true.


Featured: Evergreen Line construction image posted by nname on SkyscraperPage

We can learn from Japan on transit delays/incidents

We can learn from Japan on transit delays/incidents

Video shows that in Japan, even the train evacuations are orderly 【RocketNews24】

As reliable as Japan’s public transportation system is, with so many trains running from morning to night, eventually some sort of problem is going to occur. Passengers heading to work or school in central Kobe had their commute interrupted at approximately 8 a.m. on November 16, when it was discovered that an overhead line had snapped on the Japan Railways (JR) Kobe Line between Kobe and Motomachi Stations.

Seeing that the repairs would take some time to complete, some 5,000 passengers were instructed to leave the carriages, which were stopped in an empty stretch of the tracks, and walk to the nearest station, as directed by JR staff who were on the scene.

Even in Japan, which is known for having one of the world’s supposedly most “punctual” train systems, delays and incidents can occur. Last week in Kobe, this was the scene on the city’s main JR rapid transit line after an incident with an overhead power-line was found, requiring a full shut-down of the system in Kobe and service disruptions throughout the 194km-long intercity rapid transit line.

If this sounds familiar, that’s because it does resemble some of the incidents that have plagued our SkyTrain system here in Metro Vancouver over the past few years.

I’m also sure many of you are aware of what happened to the SkyTrain yesterday (November 24th), when it was shut down in downtown due to a “power failure” incident that turned out to be a ‘one-in-a-million’ misplaced replacement rail part that moved on the tracks and struck/damaged the power shoe of an oncoming train.

Map of JR train lines in the Osaka/Kansai area. The blue line going west-east from Himeji to Maibara through Kobe, Osaka and Kyoto was the line affected.
[OPEN to enlarge] Map of JR train lines in the Osaka/Kansai area. The blue line from Himeji in the west to Maibara in the east was the line affected.
I was in Japan last week and happened to actually experience the Kobe incident in the video at the top of this post, although I wasn’t in Kobe when it occurred. Instead, I felt the ripple effects over 140km away at Maibara Station, on the eastern end of the line, as I transferred from another train from Nagoya intending to ride this particular line en route to Kyoto.

The featured photo at the very top of this post is my own picture of the “trains delayed” notice display I ran into when I arrived at Maibara Station. I could feel my stomach churn even more when I checked the departure time-boards on the station platform itself, which showed that westbound express trains had been completely cancelled.

This left me and perhaps several hundred other passengers waiting on the platform before having to crowd onto a smaller local train, which we would ride until another station down the line (Yasu) where express trains would re-commence. The incident was uncomfortable, cost me nearly 90 minutes in delay and had a major effect on my plans for the day.

This is, incidentally, longer than the approx. 60 minute delay I experienced yesterday when I was caught in yesterday’s SkyTrain delay. I started commuting from Surrey to the Main St. Station area to fulfill an errand, right after delays began at around 2:50PM. I went through stopped trains, crowdedness of the trains and crowded-ness again when I boarded a replacement shuttle bus at Commercial-Broadway Station.

SkyTrain has been through numerous shutdowns in the past year, which many have attributed to be an issue of system reliability. In actuality, many of them the result of the lack of an auto-restart system that was neglected by BC Transit in the 1990s; some of them were genuinely due to human error; and some of them just couldn’t be prevented no matter what anyone did.

Regardless of the cause, we don’t seem to handle these very well. Doors have been broken open, resulting in people walking on the tracks unauthorized and causing further delays as track power needs to be shut down. People tend to respond loudly and angrily on social media, not waiting for the investigation to blame TransLink on whatever happens.

There’s a lot that we can learn from the Japanese when incidents like these happen. In Japan, trains are so critical to the functions of life, responsible for moving millions of people every day in a very dense country. Punctuality is considered very important, and so train operators concentrate on providing the best service possible when everything is working. It’s important to understand that things can sometimes not work – and when that happens, instructions have to be followed and anger has to be calmed. Which is why the train evacuations showcased in the video were so smooth and orderly.

This train line didn't have emergency walkways at door-level like our SkyTrain system - so passengers had to climb down ladders to get onto the track.
This train line didn’t have emergency walkways at door-level like our SkyTrain system – so passengers had to climb down ladders to get onto the track.

The most important thing to remember is that at the end of the day, these incidents don’t actually happen that often – SkyTrain has maintained a statistical reliability that tops transit systems in other cities. I pride myself over having kept myself calm throughout yesterday, and hope that other passengers who were able to do the same do so as well.

See also: Vancouverites are Spoiled with SkyTrain – Vancity Buzz

We can’t let these incidents affect the way we think about transit and play our part in shaping major transit decisions, like the recent NO vote on the regional transit referendum. It’s easy to lose sight of the facts when you’re inconvenienced and made bitter, but at the end of the day, in doing you really aren’t helping anyone.

I’m noticing many commuters on Twitter talking about how reluctant they were to take SkyTrain today. If I had let the incident from last week stop me from using the JR train line again out of fear, I wouldn’t have been able to resume with my plans to visit Himeji Castle and take these gorgeous pictures….

This slideshow requires JavaScript.

Lastly, here’s a bit from the Rocketnews article that perhaps TransLink could take from for next time…

…we think what really sealed the deal is the Japan Railways representative who shows up on the platform at the video’s 0:27 mark, ready to apologize to those who were inconvenienced and hook them up with bottles of tea, which he opens for each person who walks by. Because hey, on the occasions when you can’t be punctual, you may as well be classy.

Man tea 1

Rapid bus, SkyTrain best option for Langley

Rapid bus, SkyTrain best option for Langley

So I thought I’d put up a newsletter that the Langley Times published today, along with some added sources/notes.

For anyone that’s curious, I intend to be doing some more blogging on the BCER Interurban very shortly.

LETTERS TO THE EDITOR – Langley Times

Rapid bus, SkyTrain connection still Langley’s best option

Editor: Re: LRT announcement ignores less costly interurban option (The Times, Oct. 2)

We should welcome good transit ideas here in Langley, but there’s a reason that TramTrain isn’t one of them.

TramTrain was possible in Karlsruhe because it’s surrounded by numerous electrified regional railways. We don’t actually have that here in Vancouver; and while the BCER Interurban may seem like a tempting choice, it ran three times a day [1] and wasn’t built to service today’s cities [2].

When the province and TransLink conducted the Surrey Rapid Transit Study, the Interurban was denied because it would cost millions to retrofit yet still fall short on providing useful connections and service frequency [3]. In other words, it would be a giant waste of money.

What we do have are numerous fast highways on which we could operate inexpensive rapid buses. One of those, the Trans-Canada, now has the Fraser Valley Express (FVX) service from Carvolth Exchange to Chilliwack. This service is now providing the alternative that valley commuters asked for — but when it came time to consult locals about the FVX, Rail for the Valley did not participate [4].

That’s because Rail for the Valley’s TramTrain and LRT advocacy doesn’t come from a genuine desire to make transit better — but rather an opposition to extending SkyTrain to Langley, even though it will do the most for transit commuters.

Our SkyTrain system boasts a ridership that is higher than any LRT system in Canada and the US. That’s why over 50 cities worldwide have followed our lead by successfully employing ALRT-style driverless metros [5][6].

As an extension of an existing system, SkyTrain would have the lowest addition in annual operating costs [7]. Without transfers, commuters starting at Langley Centre Station could reach Waterfront Station within 60 minutes [8]. That’s the kind of travel time improvement that’ll get people really wanting to use public transit, and generate the fare revenue to recoup costs.

I’m all for good transit ideas; but when it comes to what will objectively serve Surrey and Langley best, rapid buses and SkyTrain are the way to go.

Daryl Dela Cruz,
Campaign manager
skytrainforsurrey.org

Footnotes

  1. BCER article in Canadian Rail No. 534 issued Jan-Feb 2010 with the writer and 4-time BCER book author, Henry Ewert, stating himself that Fraser Valley interurban trains ran 3 times per day (Mirrored on Exporail.org)
  2. An earlier technical assessment found numerous technical/construct-ability issues with interurban rail. Mirrored [HERE]
  3. Surrey Rapid Transit Study: “Compared to other alternatives, lower population and employment densities along much of the corridor and a less direct connection to Surrey City Centre would result in lower transportation benefits.” See last page of Phase II Information Boards
  4. The BC Transit Public Engagement Reports for the Fraser Valley Express, Abbotsford-Mission (CFVT) Transit Future Plan and the Abbotsford-Mission (CFVT) Efficiency Review indicate that there has been no participation by members of Rail for the Valley and other associated initiatives, with no comments on potential Interurban Rail service.
  5. The Automated Metro Observatory regularly reports on the worldwide progress of driverless transit systems. There is an expectation that the amount of fully driver-less metro systems will triple by the year 2025.
  6. In addition, numerous cities worldwide have implemented the same linear induction motor propulsion technology used by SkyTrain. A full list is on this blog: List of Linear Induction Motor rapid transit systems
  7. Funding Still Missing for LRT Operating Costs news release – SkyTrain for Surrey
  8. Based on Surrey Rapid Transit Study travel time estimates.

Surrey's LRT "Plan B" doesn't work

Surrey's LRT "Plan B" doesn't work

The media has done plenty of reporting on Mayor Linda Hepner’s desire to pursue a Canada Line P3 model to fund proposed Light Rail in Surrey, due the recent NO vote in the transit plebiscite.

Before decisions are taken from examples in this manner, I think it’s important to also take in the context of that example. In some of my most popular posts on this blog I’ve noted how a lack of context has done so much to skewer opinions and affect decisions in our region.

The Canada Line P3 was a successful P3 because its ridership and fare revenue exceeded projections.

The Canada Line’s P3 system works like this: The private partner signs on to build the line and operate for 30 years, and makes a capital investment to reduce the public funding burden. This capital investment in the project is returned as a profit through the performance payments made during operation.

If fare revenue from ridership meets or exceeds the costs, financing proceeds as planned and excess operating revenue is returned to the taxpayer. If the fare revenue does not exceed the costs, that represents significant additional costs to taxpayers to subsidize operations.

Thankfully, the Canada Line is exceeding its ridership projections, as a result of carefully considred design choices made during the decision-making process.

But, this is where the proposed ground-level Light Rail system for Surrey, which I have been a heavy critic of through the SkyTrain for Surrey website, runs into a very major problem.

The Surrey LRT system will not recover its operating costs.

It will run into an operating deficit of millions per year from opening day and it will struggle to recover these costs if it manages to do so at all.

Financial details for Surrey Rapid Transit, reported in the TransLink/MOTI joint study
Financial details for Surrey Rapid Transit, reported in the TransLink/MOTI joint study, on page 369

LRT’s operating deficit subsidy of $22 million ($2010) per year on opening day, growing to $28 million by 2041,  is on top of the $60 million per year for capital financing that Mayor Linda Hepner declared to the Globe and Mail. On top of all of these costs, additional costs would need to be added to the performance payments to the private operator, so that the partner can receive its return on investment.

When all inflation is accounted for, the cost of financing the P3 LRT will be nearly $100 million annually on opening day. The city will obviously need to find a way to come up with this money, and I take it that more than a few really big axes will be making their way to other city services as a result.

Plan Misses the Mark

Perhaps a part of the reason for this shortfall is because the City wants to replicate SkyTrain frequencies by running LRT trains at a 5-minute frequency, increasing to a 3-minute frequency after approximately 20 years. This frequency is not done anywhere else with driver-operated LRT systems in North America. The tendency is to run at 5-10 minute frequencies during peak hours only, reducing to 15 minute frequencies during off-peak hours and weekends.

Chart on SkyTrain vs a selection of LRT system frequencies. Made for a previous write-up on the Vancity Buzz.

The higher frequencies do not necessarily solve the many issues with an LRT system and the challenges such a system in Surrey will face. Of the $27 million in annual costs required to operate Surrey’s full LRT network, only $5 million is expected to be recovered through additional fare revenues. Cut the operating frequencies in half (resulting in significantly worse service), and there would still be a major operating deficit.

This is because many of the riders on the future LRT system will be people who already pay their fares on existing buses. They are the transit-dependent people of the city, not the people who may have the choice to continue to drive if that is what continues to serve them better.

A previous survey of Canada Line riders revealed that trip speed is the most liked aspect of the line. Street-level LRT’s limitation to slower street-level speeds will certainly create challenges in being competitive.

Ridership deficits

Surrey’s LRT will suffer these operating deficits because as a slower and less reliable grade-level system, it will not attract as many passengers as an integrated, grade-separated extension of SkyTrain. In addition, LRT will be unlike our driver-less SkyTrain system in that each train requires a driver, meaning it is more expensive to operate and will be subject to design limitations that will have a major effect on its viability.

Surrey’s LRT will carry only 2970 riders/km on opening day.4 The Canada Line, which carries 122,000 daily boardings2, required 100,000 (5200 passenger boardings per km) to cover its annual operating costs.3

As costly as infrastructure like the Canada Line SkyTrain is, the investment has been proven worthy by the benefits to the tens of thousands of people using the system daily. The investment confidence that has resulted in our SkyTrain system expansions needs to be applied to the whole system.
The driverless, grade-separated Canada Line hit its 2013 ridership projections more than 3 years ahead of schedule in 2010.

SkyTrain is a viable option

If SkyTrain is extended down Fraser Hwy. to Langley, it will carry 5443 riders per km on opening day.This is comparable to SkyTrain’s present system-wide average of 5693 riders per km.5

SkyTrain would offer faster, safer, and more reliable service – which would attract more ridership, generate more fare revenue and as a result cost only $6 million per year to subsidize operations.6 This would then be eliminated entirely with the concurrent optimization of local bus routes.7

Without an operating subsidy, SkyTrain would have a far better business case for a Canada Line-style P3 model. In any case, since the operations and maintenance component can be handled by the existing BCRTC, a newly created operating entity is not required. This will save taxpayers even more money as the P3 contract for SkyTrain would be a simpler Design-Build-Finance (DBF) model.

At the end of the day, I think there’s one particularly more significant number that exemplifies SkyTrain’s viability in Surrey over a ground-level Light Rail system.

SkyTrain would have a positive benefit/cost ratio of 1.45:1. The proposed LRT has a poor benefit/cost ratio of just 0.69:1.

A SkyTrain extension is clearly the only viable option for rail rapid transit in Surrey, and decision-makers in the city and elsewhere need to start taking a look at the hard facts.

Featured image: The SkyBridge, with the New Westminster Waterfront in the background. From the
Among other benefits, a SkyTrain extension will treat South-of-Fraser riders to a direct, transfer-less connection with the existing Expo Line to New Westminster and Vancouver.

Footnotes

According to data from the 2012 TransLink/MOTI joint study
Surrey Rapid Transit Alternatives Analysis (SRTAA) Phase 2 Evaluation
Available at [LINK HERE]

  1. SRTAA PAGE 369; Undiscounted value; measured over 30 years, with costs increasing to 2041 on year 2041
  2. ProTransBC (operator) website – http://www.protransbc.com/service-performance/
  3. TransLink media release – Addressing Canada Line capacity questions
  4. See SRTAA PAGE 301 for ridership estimates (divided by track lengths listed on SRTAA P. 347)
  5. Based on APTA ridership data from Q4 2014
  6. See attached graphic, or SRTAA PAGE 369
  7. Suggested on SRTAA PAGE 536: “For RRT 1A, savings of $170 million”

SkyTrain meltdowns a consequence of devaluing transit investment

SkyTrain meltdowns a consequence of devaluing transit investment

See also: Vancouverites are spoiled by SkyTrain on Vancity Buzz

2-car SkyTrain approaches Brentwood Station on the Millennium Line

Introduction

SkyTrain operates with high standards, transporting passengers with a remarkable 95% on-time performance rate and doing better at providing rapid public transit than other cities our size. However, that doesn’t mean that it’s immune to system-stopping failures that can require the use of shuttle buses and inconvenience thousands of transit passengers.

Our SkyTrain system managed to suffer from two major system meltdowns within seven days, and it’s perplexed everyone. It’s raised questions of accountability and competence within TransLink, and of the versatility of how SkyTrain is operated. It’s raised questions of whether there could be a better plan for emergencies, so as to prevent frustration and inconvenience.

By far, a lot of the comments I’ve seen point fingers at TransLink. Provincial Minister Todd Stone was quick to deny responsibility, and looking through social media reveals an aura of madness from inconvenienced customers. All of this creates a dangerous precedent that a discouragement into putting more money into our transit system is created, as people begin to believe that proactively investing in it isn’t worth it.

However, some of the problems we faced in these past 7 days could have been mitigated by just that – with investments into good maintenance of our transit system.

With the province putting TransLink through audit after audit as part of a mandate to increase the system’s efficiency, it’s become more difficult to justify investments to keep the transit system and its employees running – with everything from a provincially-funded park & ride expansion to the provision of coffee for employees to public art being put through questions and a high-level of scrutiny.

The chaos that we witnessed during SkyTrain’s recent shutdowns can very much be attributed to a devaluation of transit funding, lead by anti-TransLink campaigners.

An explanation

TransLink didn’t purchase a $20 million backup system that would have assisted SkyTrain in the event of computer failures. This would have spared riders from service meltdown incidents like the one on Thursday, July 17th.

To compound the issue, as part of the recommendations of several efficiency audits, TransLink has tightened up the amount of spare buses and staffing on the bus network. This means that when bus bridges are needed to deal with SkyTrain emergencies, there are fewer staff available to drive buses, and few buses available – which was an issue on both Thursday and on Monday, July 21st during the second, human-error-triggered meltdown.

It’s a no-win scenario for TransLink. A seamlessly-integrated backup system would not even require riders to be notified if SkyTrain were to have computer issues – and should the investment have been made known, an inevitable sensation surrounding the choice to invest – driven by anti-TransLink critics – is what we would be hearing about from the media instead. That would be the news item of the day, instead of a SkyTrain failure.

Meanwhile, continuing to provide adequate staff and buses to handle emergencies like the recent ones would go flat out against recommendations in recent audits – which could have triggered a harsh reaction from the provincial government, as they do directly control TransLink’s governance and some funding for transit.

PHOTO: Shuttle buses line up to board passengers at Metrotown
No one likes to ride a bus bridge – but it’s as important to have funding so that drivers and buses can be ready when we do need these.

Comments that put pressure on TransLink and portray them excessively negatively as an organization could result in more “NO” votes in the upcoming referendum next year. It may have become one of the reasons that TransLink has not undertaken investments proactively, spending money to prevent issues before they actually happen. As long as the public has yet to know of the real value of proactive transit investments, it’s difficult to do so without endangering long-term transit funding.

It’s a concern that has been raised by transit advocates and decision-makers, as they work hard to promote the value of transit investment in advance of this referendum. As a “NO” vote has been confirmed to be an option, there is nothing that can stop voters from using their vote to ‘send TransLink a message’ – something that would do commuters on all transportation modes no good whatsoever.

See also: Does TransLink have a bad brand? on South Fraser Blog
See also: TransLink Referendum: Can it win? What do we need to know? on Price Tags
See also: How will anti-TransLink vote influence transit referendum? on Metro 604

Last month, on Thursday and again on Monday, critics were quick to rush to mediums such as Twitter, radio and news to lambast TransLink and remind us of past issues that have been raised. The resulting negative attitude that surrounds our transit system will not just affect how people vote in the upcoming referendum – it may have numerous negative shorter-term impacts such as the reduction of fare revenue, as less people choose transit and more believe that it is not worth doing so. Less fare revenue can mean more service cuts and even worse rider satisfaction throughout the system.

I have a strong feeling that there would be a backup computer system in place today, giving riders a more reliable SkyTrain system, were it not for the persistence of the anti-TransLink critic.

“Ironically, the people campaigning to strip TransLink of funding in the name of efficiency may be responsible for the time it took to get service restored and get people moving over the last few days.”

Nathan Pachal, who operates South Fraser Blog and is running for Council in Langley Township, raised this issue on his blog in his response to the recent incidents.

What do we do about this?

We’re surrounded by comments on how TransLink is “mismanaged”. In order to effectively combat the issues that this creates, it’s important to bring into light whether this level of scrutiny and demand for cost-efficiency is actually necessary.

In a previous blog article, I brought into light how it’s questionable if TransLink was being audited correctly, pointing out a discrepancy between how cost-efficiency has been portrayed and how it’s actually supposed to be measured – noting that between the transit operators in Canada’s three major cities, TransLink is the most efficient – providing the most service at the lowest operating cost.

See also: Was TransLink audited correctly?

It’s also important to bring into light what we should already know about TransLink’s efforts to be a better organization. We should know that TransLink is following up on the recommendations in the audits, and that those efforts are working – TransLink ended financial year 2013 with a $43 million surplus.

One of the most important changes that needs to be made is in public attitudes on transit spending. We can’t be ignorant to the fact that it is necessary to spend some money to keep our system in good repair.

For SkyTrain riders, the worst part of this devaluation of transit funding is that it has a major implication on our SkyTrain system that extends beyond $20 million.

As rail lines age and ridership grows, upgrades are needed to maintain efficiency and reliability long-term, and ensure the maintenance of the benefits provided by the system. TransLink has yet to secure a long-term funding commitment to pay for the over $1 billion in upgrades that will be required to keep the SkyTrain from becoming overcrowded and unreliable as it continues to age. These upgrades will improve station facilities with new entrances and amenities, as well as prepare the system for longer 5-car trains. Some of these upgrades are ongoing, but the majority of them have yet to be started.

See also: Reality Check: Why is SkyTrain breaking down so frequently? on Vancity Buzz

Just as TransLink is looking for long-term funding to upgrade our SkyTrain system, so have other transit operators in Canada with their rapid transit systems. Calgary has made significant investments to extend C-Train platforms across the system for longer trains and refurbish old light-rail vehicles. Montreal is taking delivery of the first new subway vehicles to replace a fleet that is almost 40 years old. Toronto has been working to replace an aging 60-year-old subway signalling system and rebuild its busy downtown transit hub – Union Station – on the Yonge-University-Spadina subway line. Both projects have even required planned closures of the subway there.

Long-term funding to be committed to this upgrade is what will be decided in the provincially-mandated referendum, and it is imperative that voters do approve a funding option to keep our transit system in a good state of repair.

As costly as infrastructure like the Canada Line SkyTrain is, the investment has been proven worthy by the benefits to the tens of thousands of people using the system daily. The investment confidence that has resulted in our SkyTrain system expansions needs to be applied to the whole system.
As costly as expanding and building infrastructure like the Canada Line SkyTrain is, the investments have been proven worthy by the benefits to the tens of thousands of people using the system daily. The investment confidence that has resulted in our SkyTrain system expansions needs to be applied to the whole system.

TransLink is in trouble

Some of the issues we faced in the recent SkyTrain meltdowns definitely had to do with more than funding, and perhaps they could have been addressed through better plans and higher competence within branches of TransLink.

However, the fact remains: if we want to maintain a high or higher standard of reliability, there’s going to be an inevitable cost to it. On the other hand, if we devalue the taxes and fares that keep people moving, we don’t get a reliable system as the penalty for our ineptitude.

As stakeholders, if we want to enjoy more reliable transit, we need to realize that TransLink is in trouble and change our attitudes on transit and funding. We need to value our transit, value TransLink, and consider the good value of the services it provides to us.

My Thoughts – Re: Transportation and the July 2014 SkyTrain meltdowns

My Thoughts – Re: Transportation and the July 2014 SkyTrain meltdowns

The July 2014 SkyTrain meltdowns have probably perplexed a lot of people. In the past week, a lot of us bore witness to a level of chaos that I think had yet to be seen on the SkyTrain system in 28 years of operation.

We enjoy our SkyTrain service so much that I think that we have developed a collective expectation that things will always work out the way they’re supposed to.

Here are some of the responses I spotted on Twitter regarding the breakdown:

http://twitter.com/SantiHenderson/status/489950692669267969

http://twitter.com/BaD_KiTTy_MeLz/statuses/489943859783168001

http://twitter.com/CTVVancouver/statuses/489943945120874496

You can clearly see that there’s a lot of frustration; there’s a record of the incovenience. There’s an aura of madness that goes up in the air, as no one wants to be made late.

http://twitter.com/Charlesvancity/statuses/491315698174414848

We’re tempted to question the SkyTrain system. Bus drivers’ union leader Nathan Wood – who, on CKNW, raised an issue that Light Rail systems have outnumbered SkyTrain-type systems in terms of construction around the world, is just a bit concerned that our main rapid transit backbone can have trouble fostering a busy transit network. While his numbers on the amount of SkyTrain systems in existence are slightly off of the actual amount, I can see why people would want to raise those questions after a series of unique, 5-hour closures.

How much service was actually disrupted?

Reliability chart - SkyTrain vs other systems
Reliability chart – SkyTrain vs other systems. CLICK TO ENLARGE

You might have already seen this graphic, actually. I was wanted for a guest post on the Vancity Buzz, and had just finished creating this chart when the second consecutive major SkyTrain issue hit commuters Monday mid-day for what was unfortunately the second time in under 7 days.

SEE ALSO: Vancouverites are spoiled with SkyTrain – Vancity Buzz guest post by Daryl

Usually SkyTrain is operating for 20 hours daily – and while it’s absolutely unfortunate that the recent issues that plagued SkyTrain commuters hit during busier times of day,  a 5.5 hour meltdown constitutes just over 25% of that service – meaning service was fine for the rest of the day. This is a far better record than what was achieved during the Portland transit meltdown of 3 weeks ago, where more than 60% of service fpr the day was not on time.

In the grand scheme of things, it’s a 132 hour work-week for the SkyTrain. 5.5 hours represents approximately 4% of service provided for the week, and well under 1% of service provided for the entire year. We had this twice in one week – meaning 11 hours of service were not operated on time – but that still represents less than 0.2% of all service provided throughout the year.

SEE ALSO: Reality Check – Why is SkyTrain breaking down so frequently? – Vancity Buzz

For the rest of the year, SkyTrain is operating normally – 99.4% of service is provided, with a 94.7% on-time performance rate. SkyTrain lets us down sometimes, but this isn’t actually happening a lot of the time. We enjoy reliable, rapid service that gets us where we need to go.

On most days, we get a reliable service out of the SkyTrain system for the duration of the day.
On most days, we get a reliable service out of the SkyTrain system for the duration of the day.

What should we do about this

There’s no question that issues and system shutdowns like this can be inevitable – so is there something that we can do about it? I think that there absolutely is – and looking at these issues, it seems that there’s a lot we can learn from this. For example – a lot of the time SkyTrain will fail, it impacts all riders because many bus lines connect to SkyTrain stations. A strategy to minimize delays during system shutdowns could involve the redirection or extension of bus routes to key areas to serve riders where they already are.

Normally, the best transit agencies can do when this happens is implement a shuttle bus bridge to repace the rapid transit service. This was the same procedure in Toronto and Portland, as pointed out above. The bus bridges are released as demand allows, but there’s no specific protocol that is followed in the event of a failure – meaning it can take some time before the bus bridges actually start, with passengers delayed until then.

PHOTO: Shuttle buses line up to board passengers at Metrotown
No one llikes to deal with slower shuttle buses replacing SkyTrain service!

But, it’s important to be prepared.

So, here’s an important disclaimer: I was lucky enough to not be there for both of these recent SkyTrain disruptions.

But, before you lambast me with comments of “you don’t know what we face!” or “try being on a train when it happened”, I would like to comment that I have seen my share of SkyTrain delays and disruptions before.

Prominent was the one that hit our system in April 2013, when a power rail issue in New Westminster halted trains on the system for close to an hour and required the deployment of shuttle bus bridges. I was on the problem train, and remember what it felt like as my train was passing the problem area and the electricity was suddenly cut. I remember how staff restarted the train and tried to move it past the area again, only for it to once again come to a grinding halt. I was heading from Surrey to the last showing of the theatre play at Windermere Secondary School, to see the performance and meet some friends in a yearly event that I consider to be something of a tradition. With the level of delays, I was unfortunately not able to make it to Windermere until the play ended.

It’s important to remember that transit isn’t the only form of transportation that isn’t always reliable. Accidents on key arterials or bridges can disrupt the flow of traffic in the region, especially when there are two or more bridges blocked at the same time. As a driver, you might know an alternate route that might be slower but will get you there with less congestion and less time waste. I think the same needs to be true for riders of transit.

Sometimes, there’s just no way to make it on time. Regardless, I still think it’s important to be somewhat prepared for when there are issues – and handle ourselves calmly and responsibly in times of crisis.

Gas prices of late are reaching all-time highs in Metro Vancouver. Source: Vancity Buzz
Gas prices of late are reaching all-time highs in Metro Vancouver. Source: Vancity Buzz

There’s an important message that can be had from the recent issues, one of which is a need for all of us to step back and realize that every possible way to get around has some sort of volatility. Even as we walk, we risk tripping on something that can temporarily impair our most basic ability to get around. The reality is, no matter how we choose to get around, we may run into issues. And, with the amount of money we sink into our demand to get around, it’s understandable why there’s such a high level of frustration when a transportation service you must rely on does not work out – not just on the SkyTrain but everywhere else.

Think about it. It’s true, right? So much of the money we earn goes towards the basic function of getting around. Transportation defines the way all of us live – so much that I think we don’t realize that it costs a lot of money to get around in this society. We take our transportation for granted – and for the younger ones, who may have benefited from the subsidized and discounted U-PASS, it’s especially not easy to realize this. However, this is the reality of the life we live. An average suburban household might spend more than 60% of income on the house and car – dealing with gas prices at all-time highs and ownership costs.

But where do I start?

It all starts with looking at where you live and where you might be going, and looking at your alternatives well in advance. For example: what are the bus routes near your house, and where can they take you. Which routes are your best options (accounting for frequency, speed, etc.) Or, if you live in Surrey and you tend to need to get across the Fraser River a lot, how much money can you set aside in case you need to pay for a cab to get across? If you vaule your money, what are the alternate bus routes to get you around once you do get across? (for example: the 123 from New West Station goes to Brentwood, or the 100 22nd St Station goes to South Vancouver).

As a society, we have to be anticipative of issues and have the knowledge to deal with it in real time – because often, transit authorities have limited resources and can’t always do that.

Appendix

Anyway, to conclude this, I’ve seen the comments to the Vancity Buzz post on Facebook, etc. and some of you asked for the sources for my on-time performance numbers – which I have listed below.

I know it’s questionable given I have omitted certain systems, so to clarify – if there’s a system I omitted, it may be because of the difficulty in actually finding the numbers (the internet, in a limited time frame, can only get you so far!) or due to measurement standards that weren’t too comparable (I was looking at adding some Light Rail systems in New Jersey to the list, but NJ Transit’s stats measure with poor standards that consider runs on-time even if they are 6 minutes early or late, so I chose to omit). Listed below:

The consequences of this BC educational conflict are real

The consequences of this BC educational conflict are real

Above video: the Johnston Heights senior choir performs for students

At Johnston Heights Secondary in Surrey, where I completed my grade 12 education early last year, the ongoing disputes between teachers and the government have caused the cancellation of at least one major school event, one of which I was looking forward to attending: the year-end music (band and choir) concert.

The J.H. Music Program is one of the best in the city, having participated in numerous major provincial events such as MusicFest in Ottawa, 2010 (earning the silver award for both band and choir), several consecutive Kiwanis Music Festivals, and the Envision Jazz Festival in Surrey. As an alumni of this program and a member of both the senior wind ensemble and jazz band, I cannot stress enough how important the year-end concert is in the spirit of learning and school culture.

The year-end concert is a celebration of music and school culture, and it represents the culmination of a year’s worth of practicing, learning, dedication and team-building. It attracts other students, parents, and alumni who were in the music program to witness the music-making talents of a new generation of students who participate in the Grade 8, 9 and 10-12 senior bands; the grade 8, 9-10 junior and 11-12 senior choir; the chamber choir; the string ensembe; and the intermediate and senior jazz bands. The latter four are courses that are held outside of the school time and are the culmination of willful attendance, participation and commitment from both the teachers and the students who are involved.

With the school inaccessible outside of normal school hours (which is also preventing students from using the bandroom facilities for practice), this event has been put off indefinitely for the year 2014. It may be the first year in several consecutive years that the school music program did not hold a year-end concert, and I am sad to see that my peers aren’t going to be able to celebrate their hard work and dedication to music.

This is just one of the many inconveniences students have to face because of the ongoing conflict between teachers and the government. Not just now, but in the past several years of deteriorating school conditions.

North Surrey Secondary's 5 block schedule

At the North Surrey Secondary school here in Surrey, too many students and an overcrowded school building have forced the school to adopt an awkward five-block schedule [CLICK HERE]. NSSS staggers students across the 5 blocks, so that older students study for the first four and younger ones for the last four (or combinations with study blocks).

I have often – in letters to the editor, and in other posts on this blog – discussed the realities being faced by students not just in the current conflict but on a year-by-year basis. Not far from Johnston Heights Secondary and at North Surrey Secondary, 5-block schedules are needing to be adopted to deal with increased overcrowding, lack of facilities, and growth in the community.

In the same manner as North Surrey, many schools have been forced to make serious, critical cuts to deal with cut funding levels and increased teacher stress. I’m not sure if North Surrey still requires a 5-block schedule this year, but I was hearing about it from numerous close friends when I was in high school – and I was also hearing about the troubles this schedule gave them – troubles in scheduling conflicts and stress.

See also: The Real Reason Children Have Lost the Freedom to Roam

One of the dangerous criticisms I’m hearing in the current debate is how kids are being used as “bargaining chips”, resulting in the implication that the teachers fighting their battle over class sizes and competition and pay levels are careless.

However, critics also forget that many teachers have kids too – and these kids are as much participants in the pubic education program as the ones who are being taught. Many of the teachers I personally knew were parents of one or more kids, and a few of them gave birth to new kin while I was in my high school years. In the short term, these kids will theoretically suffer as much from their parents’ course of actions as the rest of the students participating in this school system, and I think it shows that what the teachers are fighting for is more than just their own living conditions and demands. I think it is evident that it is also about good learning conditions for their kids and ours.

SkyTrain critics deny benefits of driverless rail

SkyTrain critics deny benefits of driverless rail

Transit gurus in the region constantly criticize SkyTrain and it doesn’t make sense.


I think I’ve pretty much seen it all: unfound claims on SkyTrain’s financial burden, claims that entire tram networks could be built at the same cost as a SkyTrain extension (ignoring the impracticalities of trying to conduct such a massive replacement of buses without ever improving transit speed), and other alternate light-rail transit (LRT) proposals that just don’t make any practical sense.

SkyTrain is constantly being challenged, and this contention has had a phenomenal effect in getting people involved with transit planning matters. Some of the biggest names we know in Metro Vancouver transit issues discussions – the ones you might hear about in newspapers; examples include: Paul Hillsdon, Nathan Pachal, Jordan Bateman, John Buker – are or at one point have been motivated by a criticism of SkyTrain rapid transit.

If there were no one to respond to these criticisms and unearth the problems with such a viewpoint – as I am doing so now – the quality of transit planning in Metro Vanouver would deteriorate to the point where perhaps no disagreement would be had on transit projects; and consequently, little progress would be made in changing communities and peoples’ lives for the better.

Denying the Benefits

SkyTrain critics deny SkyTrain’s potential as a high-quality rapid transit system. They don’t even want to see it acknowledged that SkyTrain generates billions of dollars in transportation, developmental and economic benefits. They clutter our blog-feeds, newsletter sections and comments with endlessly varied suggestions to perpetuate the belief that SkyTrain simply isn’t the best option for investment.

They’re often proponents of Light Rail Transit (LRT), an alternative option that could allow rail transit to be built in a somewhat more flexible manner (including at-grade and on-street), who are quick to bring forward the positives of community-building, lower capital cost and less obtrusive (at-grade) infrastructure as upsides when compared to SkyTrain.

Can LRT be an appropriate solution in the transit planning sense? Absolutely. That should be quite obvious: there’s a reason why light rail investments are so popular around the world, with hundreds of proposals to reference at any time. However, the versatility of LRT should not be resulting in the dismissal of SkyTrain as another great – and often better – solution to addressing transportation problems, especially here in Metro Vancouver.

And yet, the critics are relentless in their criticisms. . Worse – they’re ridiculing and, apparently, finding reasons to shame our system and the way we’ve built it. These are the worst kind – the kind that try to deny altogether that building SkyTrain has provided Metro Vancouver with any benefits – and the ones who should arguably be disallowed from participating in public policy debacles, because they seem to have no understanding of what has been happening here in Vancouver for the past 30 years.

Metrotown has been phenomenally influenced by the introduction of SkyTrain. In the past 9 months I have spent living in Burnaby, I have witnessed the growth of at least 6 new high-rises.
Metrotown has been phenomenally influenced positively by the introduction of SkyTrain. During the year I spent living in the Burnaby area, I witnessed the growth of at least 6 new high-rises. You can see many of them in this photo.

Sample contentions by SkyTrain critics that are incorrect

1. SkyTrain hasn’t gotten people out of their cars.

TransLink’s trip diary data is a difficulty: there is little bearing that can be had about the accuracy of the measurements (this is a sample size) and the types of commutes that were recorded (i.e. are they commutes to work, shopping, and at what time of day/day), but nevertheless, it is a valid source. It’s used by TransLink and Metro Vancouver in regional planning matters,  and is and often utilized by SkyTrain critics. As SkyTrain critics have been quick to point out, the 2011 value is only 3% higher than the valule recorded in 1994 – the year SkyTrain was expanded across the Fraser River and into Surrey. It’s tempting, when you look at this, to think that SkyTrain has failed us in serving its original purpose.

The problem with these numbers is that they really don’t tell the whole story.

The trip diary draws data from 22,000 households in the region, and is meant to take a “snapshot” of a day in Metro Vancouver transportation. It is a partial survey – it’s not the same as the much more accurate ‘journey-to-work mode-share’ numbers collected by Stats Canada from every household, which show that transit mode share in Metro Vancouver is a bit higher than that collected in the Trip Diary and – together with walking and cycling – has grown significantly since 1996.

Closer studies have suggested that the biggest impact in transit modal shift is coming from SkyTrain and SkyTrain expansion. The City of Vancouver has also collected more specific numbers [Vancouver Transportation Plan Update – CLICK HERE] that not only show a big increase in transit ridership from outside of the city (i.e. connected by SkyTrain) – but also that the amount of motor vehicle trips actually declined for the past decade, despite population growth.

An even closer 2009 study [Niko Juevic SFU study – LINK HERE] that more closely looked at households within both 400m and 1500m radii of Expo and Millennium SkyTrain stations showed even more significant changes – outpacing transit modal shift across the region. The opening of the Millennium Line SkyTrain had a phenomenal effect on the surrounding area: within a 1500m radius of each station, transit mode-share had nearly doubled 4 years after the line opened – growing at more than 4x the regional average rate.

I compiled a summary of these numbers in the graphic below:

Modal shift in Vancouver - data compiled from Statistics Canada, Metro Vancouver and 2009 study by Niko Juevic

2. 80% of SkyTrain riders are recycled bus riders

South Surrey Park and Ride's Expansion Lot. CC-BY; Photo credit: Tay.Freder on Flickr
351 buses at Bridgeport Station wait to depart for South Surrey Park & Ride. Photo credit: Flickr – Stephen Rees

While I’ve never really been able to track a definitive source for this statistic (I have seriously only ever heard it from one SkyTrain critic group), I see it repeated in discussion circles and used as justification that SkyTrain is weak at attracting ridership. SkyTrain critics have repeated this number to contend that the majority of riders on the SkyTrain were already taking transit before the line was built, claiming that this is “double the industry standard” – and were extremely vocal in certain situations where SkyTrain expansion replaced one or mutliple bus routes, especially in the case of the Canada Line (which replaced express segments for multiple south-of-Fraser bus routes heading into Vancouver).

Firsty, I have never understood why such a vague 80% number is being portrayed as a weakness. In the City of Calgary, a single centralized high-density core and the most expensive downtown parking in North America combine with free park-and-ride facilities along Light Rail Transit lines to give the Calgary C-Train the majority of its nearly 300,000 daily boardings. The Calgary C-Train is a versatile system and many of its riders have chosen to use transit, but not for their entire commute – the first segment of their trips is more often being done by car than by bus, walk or bike.

If the majority of SkyTrain riders are taking other transit to get there first, then that is at least as much a strength as much as it is a weakness (and, very likely, very much more a strength) – because this kind of transit commute coherency is simply not being replicated by other rail transit systems.

The versatile Calgary C-Train services nearly 300,000 boardings every day - but outside of the city core, Park'n'Rides such as this one contribute the majority of C-Train ridership. Image source: Calgary Transit website
The versatile Calgary C-Train services nearly 300,000 boardings every day – but outside of the city core, Park’n’Rides such as this one contribute the majority of C-Train ridership. Image source: Calgary Transit website

Secondly, this claim – at least in the case of the Canada Line – certainly doesn’t hold up to collected ridership numbers.

Passenger measurements by Canada Line operator ProTransBC collected by the Richmond Review were showing that Canada Line ridership in its first few weeks averaged 77,000 – meaning over 55% of today’s ridership numbers were already on board the Canada Line before September 7th, 2009 – when the 98 B-Line and 490-series express routes were terminated, and the many South-of-Fraser express buses (351, 601, etc) were terminated at Bridgeport rather than continuing to downtown Vancouver.

These bus routes make up only a small percent of the Canada Line’s total ridership – the vast majority were choosing to ride the Canada Line before any of these buses were transferred to terminate at Bridgeport or eliminated. A rider survey conducted in 2011 indicated that 40% of those surveyed were new to the system – that being, they previously drove and did not take transit at all for that commute – and that riders’ biggest vaues for the system were speed, frequency and reliabillity.

With the cancellation of the 98 B-Line and associated peak-hour express routes, it’s true that a number of the Canada Line’s passengers were riders of the previous bus-only system; however, this is something that needs to be expected from all rapid transit projects regardless of technology and alignment. Each and every SkyTrain line, C-Train Line, Portland MAX line, etc. replaced a previous bus service and took in riders from that bus service.

Claims like this also downpay the benefits being provided to any previous bus riders, whose faster commutes are fostering increased productivity, lower stress levels and better comfort. For most of the first month of operation, the 98 B-Line continued its operations alongside the new Canada Line until its termination on September 7th. Riders had the option of continuing to ride the 98 or take the new SkyTrain – and as evidenced by ridership numbers that averaged more than double what the 98 B-Line carried before the new SkyTrain opened, the majority of 98 riders were opting for the faster ride.

The proof is in the ridership

A Canada Line train pulls into Marine Dr Station - photo by Larry Chen, license obtained
A Canada Line train pulls into Marine Dr Station – photo by Larry Chen, license obtained

See also: Surrey’s Next Mayor should Push for SkyTrain – Surrey Leader letter

The Canada Line, which was introduced just 4 years ago, is already a Vancouver icon; a part of this city’s fabric of life. It’s hard to believe that less than 5 years ago, the link between downtown Vancouver and Richmond was a miserable bus trip that took as long as the SkyTrain’s Expo Line took to travel nearly twice the distance to Surrey. As a daily rider of the Canada Line to reach Kwantlen University in Richmond (and again later in the day to go from there to work downtown), the Canada Line’s benefits are evident to me in person. I don’t have to worry about potential traffic issues heading into Vancouver that can make buses (or even light rail trains) late – and neither do the 121,999 others who ride with me each and every day.

Riders, stakeholders and decision makers have been clamouring to build something similar and soon under Broadway between UBC and Commercial-Broadway Station. Support has been near unanimous, because previous experience with SkyTrain has shown us that we can be confident about the expanding the system.

Local mayors who were concerned that the expense of SkyTrain would make TransLink’s assets like electric trolleys “crash” were proved wrong when the Canada Line exceeded ridership expectations well ahead of time.

In walks of transit planning and provision, I have always thought that SkyTrain isn’t getting enough credit for what it does. SkyTrain has been part of why Metro Vancouver has lead North American cities in transit ridership. We rank third in transit trips per person per year, behind only New York and Toronto.  We’re ahead of Montreal, Boston, and Washington, D.C. – cities with full-size metro systems – and far ahead of cities with only LRT systems. This has grown from 4th in 2006.

We are achieving great things because we approved the construction and expansion of the SkyTrain system. Which is why making sure SkyTrain critics who mess up the facts do not get a grip on transit-planning decision makers is my top priority for this year.

SkyTrain critic's "alternative" to Broadway subway is half-baked

SkyTrain critic's "alternative" to Broadway subway is half-baked

Introduction

Critics of SkyTrain as a technology and rapid transit option are everywhere. Largely motivated by a fear of all megaprojects with high capital costs, SkyTrain critics are vocal, active, and will stop at nothing to act on this fear. They deny the productivity and developmental benefits that the system has given our region, and they refuse the potential that SkyTrain has to continue to be useful to our region if extended further.

With a $3 billion capital cost, it’s no surprise that numerous SkyTrain critics, fearing the investment cost, have scrambled to promote or find alternatives. “Just another SkyTrain critic” was my first response when I first read about an “alternate proposal” for a Light Rail Transit (LRT) line on 16th over a Broadway subway crafted together by Adam Fitch – a planning technician for the Thompson Nicola Regional District – just over 1 year ago when it was featured suddenly in the Vancouver Sun.

But, the response seemed to be triggered by an absolutely valid series of concerns over the impact on businesses on Central and West Broadway if an at-grade LRT were to be built on Broadway itself – including the loss of parking, impacts to parallel cycling routes, and expropriation at a few properties (particularly at Broadway and Kingsway/Main) where it would indeed be necessary. I suspected that Fitch crafted the idea to counter the imminent disappearance of LRT consideration from public policy in Vancouver.

Graphic showing Adam Fitch's LRT proposal - as reuploaded onto the Georgia Straight
Graphic showing Adam Fitch’s LRT proposal

Forget about a Broadway subway, think LRT along West 16th – Vancouver Sun

…The most appropriate solution, with due consideration for costs, regional transit priorities (i.e. Surrey, etc.) and time frame (10 years from now to build the subway at a minimum) is to build a mainly street-level light rail along the CPR corridor, the Arbutus corridor, and West 16th Avenue to UBC. Compare this route with a Broadway subway on cost, construction time and capacity, and it prevails. [READ MORE]

Over the years, this idea continued to circulate in the local discussion scene. It has been featured on a number of regional transit issues outlets, including: Price Tags, Stephen Rees, Rail for the Valley (obviously) and – most notably, but not surprisingly given the paper’s perpetual pro-LRT bias – the Georgia Straight newspaper, in a feature with an intimidating headline that immediately implies that the alternative is “better” – or at least, as reviewed by editor Stephen Hui.

Critics of the planned Broadway SkyTrain wasted no time backing this idea, calling it the next big thing, triumphing it as a “realistic priority” and denouncing the SkyTrain extension proposal as “another megaproject” in the comments for this article.

I find it unfortunate that these people were given this opportunity to further this cause, because it honestly surprises me that the idea – despite the objections from many others aside from myself – has not already died. The fact of the matter that some editors at the Georgia Straight (among others) haven’t seen is that the 16th Ave LRT and B-Line combo idea is a poor, discredited and badly planned idea from someone who doesn’t have a clue how this city works.

A 16th Ave LRT just doesn’t work

I contend that advocating for this idea is a collosal waste of time and money for three simple reasons:

  1. No benefits to Central Broadway riders

  2. Few, if any, benefits to UBC students

  3. Doubling of annual operating debt

Let’s put it into context:

Map outlining LRT proposal by Adam Fitch, planned Broadway SkyTrain and major Broadway business and activity areas.
Map outlining LRT proposal by Adam Fitch, along with planned Broadway SkyTrain and major Broadway business and activity areas. Dashed portions in tunnels.

Take a look at this stylized map showing both the routings for the planned Broadway SkyTrain extension and Adam Fitch’s LRT proposal. Notice how the planned Broadway SkyTrain services all of the busy business and activity districts on Broadway, but the LRT misses them – making the only possible benefactors the rider from either existing SkyTrain Lines, Broadway & Arbutus, and residents along the 16th Avenue corridor.

What this show is that there are clearly no benefits to Central Broadway riders – which actually make up a significant majority of the current 99 B-Line’s ridership, as opposed to UBC – and the West Broadway business district is missed as well. That’s millions of dollars in economic potential that could be unlocked, but that isn’t happening under Fitch’s plan. In what would quite possibly be the least equitable planning move in Metro Vancouver transportation planning history, billions of dollars would be spent to benefit only a small portion of the tens of thousands who are actually facing the problems that riders are facing on the Broadway corridor daily.

RRT ridership boardings and alightings on Broadway - from TransLink report, referenced on Voony's blog
RRT ridership boardings and alightings on Broadway – from TransLink report, referenced on Voony’s blog

As many, the Adam’s proposal apparently assumes that the main demand is on UBC. It is worth to mention that the numbers ran by Translink suggests that the highest demand is on the central Broadway portion (Voony’s Blog)

It was one of the shortfalls I mentioned in my original letter to the sun responding to the concept. The City of Vancouver’s report on Broadway rapid transit finds that the Central Broadway area generates at least as many trips as UBC, if not more.

It is extremely important to bring any rapid transit to where the anchors and trip generators actually are – both at the ends and along the route itself. That’s why the Canada Line uses the Cambie Street corridor, as opposed to either Granville or Arbutus Streets – because it provides strategic connections to busy anchors like Central Broadway, City Hall, various major hospitals, Queen Elizabeth Park, and Oakridge Mall along the way.

Map outlining LRT proposal by Adam Fitch and major Broadway business and activity areas.
Here’s the same map again, but with the LRT proposal on its own. See the discrepancy?

The indirectness of the proposal also has some other consequences: the proposal is 2.3km longer than any route going down Broadway, an additional distance that not only adds to the proposal’s capital costs – it brings up the travel times as well.

the Adam Fitch LRT proposal is 2.3km longer than any route on Broadway, including the current B-Line
the Adam Fitch LRT proposal is 2.3km longer than any route on Broadway, including the current B-Line

On top of the longer line distance, while parts of the line will be capable of 80-90km/h operation like SkyTrain – supported by crossing gates and some tunnelling – there are several portions of the line that will need to be limited to 50-60km/h speed limits – further dampening the supposed speed benefit:

Speed restrictions on some parts of the proposal corridor, limiting trams to the speed of the parallel road, are necessary in order to maintain community safety, structure and integrity.
Speed restrictions on some parts of the proposal corridor are necessary in order to maintain and preserve community safety, structure and integrity.

As a result of the longer distance combined with the speed restrictions, the proposal fails to offer a significant benefit to the one possible travel crowd that could seriously benefit: the UBC traveller; which brings me to my second contention: the Fitch proposal offers few, if any, benefits to UBC students.

With the longer route and deferred connections, it’s reasonable to think that many riders – especially in non-congested off-peak hours, when the 99 B-Line trip takes as little as 30-minutes end-to-end – will opt to continue using the 99 B-Line on Broadway.

This especially applies for UBC students who live on campus, where the 99 is an important connection to businesses in Point Grey/Sasamat, West Broadway and Central Broadway. Fitch’s proposed LRT links fewer business centres, with the first major business cluster from UBC being reached when the line hits Dunbar – a full 6km away, twice as far as Sasamat. Meaning, for items and needs like groceries, doctor’s appointments and other outings, UBC students likely won’t be utilizing the billions of dollars spent on Fitch’s LRT – they’ll be continuing to use the 99 B-Line.

Which brings me to the third reason why Fitch’s LRT proposal is an extremely bad idea: with the required retention of the 99 B-Line, the Fitch LRT proposal doubles the annual operating debt of providing Broadway-UBC corridor transit. By not replacing the 99 B-Line, the operating cost of providing UBC-Broadway corridor transit can only increase.

Versus the current (“business-as-usual”) setup that includes the 99 B-Line, the planned Broadway SkyTrain is expected to save $7 million incrementally in annual operating costs (see: design guide). With estimates already pitting the operating cost of a separate LRT on Broadway itself at over $10 million annually by 2041 (in 2011 dollars), the operating debt with the Fitch LRT simply doubles over the existing setup.

The bigger picture

I could go so far as to say that the Fitch LRT proposal hurts the entire region, because it is really that short-sighted in terms of practical thinking.

As aforementioned, the planned driverless SkyTrain extension is expected to save $7 million in annual operating costs – savings that could be redirected to improving transit around the region. With over 54,000 new transit trips daily attracted around the region – more than double other studied options, including any theoretical LRT on Broadway itself – the planned Broadway SkyTrain generates new fare revenue. That would have also been a serious contributor to expanded transit around the region.

The elimination of the 99 B-Line also means bus services improve throughout the region – because the 99 B-Line consumes more than half of TransLink’s articulated diesel bus fleet. These buses could be redirected to other busy routes in the region to address growing transit demands.

With the Fitch LRT proposal, none of these improvements are able to materialize.

The introduction of the Canada Line and the displacement of several articulated 98 B-Line buses allowed capacity to be improved in services around the region, and in new travel markets such as Surrey. Seen here isa 96 B-Line bus departing Newton; the bus rapid transit route was introduced in Surrey just last year. Photo credit: The Buzzer
The introduction of the Canada Line and the displacement of several articulated 98 B-Line buses allowed capacity to be improved in services around the region, and in new travel markets such as Surrey. Seen here is a 96 B-Line bus departing Newton for Guildford; the express B-Line route was introduced in Surrey just last year. Photo credit: The Buzzer

Such bus service redirection can also take from the numerous other high-frequency bus routes that connect to UBC from different parts of the city, usually during peak hour periods. These are the:

  • 43 Joyce Station – via 41st Ave and Oakridge
  • 44 Downtown – via 4th Ave
  • 84 VCC-Clark Station (ALL-DAY) via 4th Ave, Olympic Village and Great Northern Way
  • 480 Bridgeport Station (ALL-DAY Weekdays) – via Kerrisdale and Marpole

The planned Broadway SkyTrain is the only option that offers the significant travel time benefits (cutting travel time between Commercial-Broadway and UBC in half, to 19 minutes!) that could enable the truncation of some of these routes to save even more money annually. For example: the 44 duplicates the 84, and is likely to be eliminated in favour of the faster connections downtown riders will get by utilizing the Broadway Subway with connecting routes and the Canada Line. The 480 could also be eliminated, perhaps following my suggestion. However, with the incremental operating cost savings, bus service on even these routes could theoretically be increased without costing more than the transit on the Broadway-UBC corridor today.

By denying these benefits and choosing an alternative simply because it offers the prospect of less initial capital cost, the region loses out on better transit both on Broadway itself and elsewhere.

Conclusion

Responding to the Straight over the mention of Vancouver Mayor Gregor Robertson being on record for supporting the planned Broadway SkyTrain extension, Fitch rather arrogantly proclaimed in the opening of the recent article on his proposal:

“He’s wrong on probably four or five fronts.”

But, as an upvoted commenter pointed out, he didn’t list a single one. Which I think highlights another problem with critics who fear studied and decided megaprojects and act quickly to try and debase them: they don’t do a good job at it. In this case that doesn’t help, because I think that the City of Vancouver has done an excellent job at laying down the benefits and the business case of a Broadway SkyTrain extension – probably much to the dismay of many critics who have already quit.

As for Adam Fitch’s 16th Ave LRT proposal, it’s evident that not only does it have no case – it really has no argument either.

*****

Author’s note: Thanks for reading this far! I encourage you to subscribe to my blog by clicking the “follow” button on the left sidebar! As I previously mentioned, I will be detailing why there is really no alternative to the Broadway subway – how its business case is proven, and why any alternatives just do not work – in a follow-up article.